I have created two select clauses for counting weekdays. Is there a way to combine the two select together? I would like 1 table with two columns:

Jobs Complete Jobs completed within 5 days

10 5

-

SELECT COUNT(DATEDIFF(d, DateintoSD, SDCompleted) - DATEDIFF(ww, DateintoSD, SDCompleted) * 2) AS 'Jobs Completed within 5 days'
FROM dbo.Project
WHERE (SDCompleted > @.SDCompleted) AND (SDCompleted < @.SDCompleted2) AND (BusinessSector = 34) AND (req_type = 'DBB request ') AND
(DATEDIFF(d, DateintoSD, SDCompleted) - DATEDIFF(ww, DateintoSD, SDCompleted) * 2 <= 5)

Select COUNT(DATEDIFF(d, DateintoSD, SDCompleted) - DATEDIFF(ww, DateintoSD, SDCompleted) * 2) AS 'Total Jobs Completed'
From Project
WHERE (SDCompleted > @.SDCompleted) AND (SDCompleted < @.SDCompleted2) AND (BusinessSector = 34) AND (req_type = 'DBB request ')

2 ways of the top of my head:

1

select Z1.[Jobs Completed within 5 days], Z2.[Total Jobs Completed]

from

(

SELECT COUNT(DATEDIFF(d, DateintoSD, SDCompleted) - DATEDIFF(ww, DateintoSD, SDCompleted) * 2) AS 'Jobs Completed within 5 days'
FROM dbo.Project
WHERE (SDCompleted > @.SDCompleted) AND (SDCompleted < @.SDCompleted2) AND (BusinessSector = 34) AND (req_type = 'DBB request ') AND
(DATEDIFF(d, DateintoSD, SDCompleted) - DATEDIFF(ww, DateintoSD, SDCompleted) * 2 <= 5)

) Z1,

(

Select COUNT(DATEDIFF(d, DateintoSD, SDCompleted) - DATEDIFF(ww, DateintoSD, SDCompleted) * 2) AS 'Total Jobs Completed'
From Project
WHERE (SDCompleted > @.SDCompleted) AND (SDCompleted < @.SDCompleted2) AND (BusinessSector = 34) AND (req_type = 'DBB request ')

) Z2

2

select

(

SELECT COUNT(DATEDIFF(d, DateintoSD, SDCompleted) - DATEDIFF(ww, DateintoSD, SDCompleted) * 2) AS 'Jobs Completed within 5 days'
FROM dbo.Project
WHERE (SDCompleted > @.SDCompleted) AND (SDCompleted < @.SDCompleted2) AND (BusinessSector = 34) AND (req_type = 'DBB request ') AND
(DATEDIFF(d, DateintoSD, SDCompleted) - DATEDIFF(ww, DateintoSD, SDCompleted) * 2 <= 5)

),

(

Select COUNT(DATEDIFF(d, DateintoSD, SDCompleted) - DATEDIFF(ww, DateintoSD, SDCompleted) * 2) AS 'Total Jobs Completed'
From Project
WHERE (SDCompleted > @.SDCompleted) AND (SDCompleted < @.SDCompleted2) AND (BusinessSector = 34) AND (req_type = 'DBB request ')

)

|||